Menu Bar and Toolbar Information
Menu Bar and Toolbar Tables
Section titled “Menu Bar and Toolbar Tables”Menu Bar
Section titled “Menu Bar”| Item | Description |
|---|---|
| New - Project | Opens the New Project window to create a new project. The currently opened project will be closed when a new project is created. |
| New - Page | Creates a new graphic page for the project. |
| Opens a file explorer window where users can select a “.cnvs” format project to launch the last-edited version of that project. When a project is opened, the currently opened project will be closed. | |
| Open Recent | Opens a dropdown that shows up to the last 16 edited projects. If a project is clicked, the last-edited version of that project will be launched. When a project is opened, the currently opened project will be closed. If a project was built in a higher version, it cannot be opened. Additionally, if a project’s path has been changed, the project’s new location will not appear in the recent project sections. |
| Close - Project | Closes the current project. If changes to the currently opened project are not saved, a dialog box requesting the user to Save, Don’t Save, or Cancel will pop up. |
| Close - Page | Closes the current page. |
| Close - All Pages | Closes all pages on the current project. |
| Saves the project’s current status. | |
| Copies the current project to a specified destination. | |
| Project Properties | Opens the Project Properties window to customize the user’s project. |
| Convert Project Size | Opens the Convert Project Size window to change the project’s set size. |
| Designer Settings | Opens the Designer Settings window to change a few settings not found in Project Properties. |
| Exit | Terminates the Canvas program. If changes to the currently opened project are not saved, a dialog box requesting the user to Save, Don’t Save, or Cancel will pop up. |
| Item | Description |
|---|---|
| Reverts the last non-undone action made. | |
| Reverts the last non-redone undo action made. | |
| Deletes the selected object’s content and saves it in the clipboard. | |
| Saves the selected object’s content in the clipboard. | |
| Pastes a cut or copied object from the clipboard. | |
| Delete | Deletes the selected object. |
| Select All | Selects all of the objects on the current page. |
| Deselect | Deselects all currently selected objects. |
| Opens the Find and Replace window to allow users to change the set text and colors of objects and tags. |
Find and Replace
Section titled “Find and Replace”| Item | Description |
|---|---|
| Property Type | Sets the type of string that will be searched. The options available are Text and Color. |
| Scope Type | Sets the location that will be searched. The options available are Global and Pages. |
| Search Scope | Sets the type of objects that will be searched through. The options available are All, Object Properties, Page Properties, Project Properties, Scripts, Tag Database, I/O Devices, Data Server Devices, Alarms, Data Loggers, Security, Scheduler, Translations, and None. There is an option in the dropdown to select or deselect every option. |
| Search For | The given text that will be searched in the current script. |
| Filters occurrences of the Search For field using Regular Expression statements. This form uses a case-sensitive approach of a character followed by a number of “.”, and then another character. This will search for any string or portion of a string that starts with the first given character, followed by the number of “.” as placeholders, and ends in the second given character. | |
| Filters occurrences of the Search For field to be case-sensitive. | |
| Filters occurrences of the Search For field to show only strings that are complete words. This entails having no extra or missing characters and beginning and ending with whitespace. | |
| Search | Uses the current configuration to search for the given text in the Search For field to populate the table. |
| Result Type | Displays the object type that a string belongs to. |
| Item Name | Displays the name of the object that the string belongs to. |
| Property Type | Displays the field that the string is applied to. |
| Value | Displays the entire set of words that includes the searched string in the specified object. |
| Previous | Selects the occurrence in the table preceding the selected object. If there are no preceding occurrences, the selection advances to the end of the table. If no occurrence has been selected, Previous will be evaluated at the first occurrence. |
| Next | Selects the occurrence in the table succeeding the selected object. If there are no succeeding occurrences, the selection returns to the beginning of the table. If no occurrence has been selected, Next will be evaluated at the first occurrence. |
| Replace With: | The given text that will replace all occurrences of the Search For field when clicking Replace Selected or Replace All. |
| Replace Selected | Converts the selected occurrence of the given text in the Search For field to the new given text in the Replace With field. |
| Replace All | Converts all occurrences of the given text in the Search For field to the new given text in the Replace With field. |
| OK | Closes the Find and Replace window. |
| Item | Description |
|---|---|
| Project Tree | Controls whether the Project Tree pane is visible or not. |
| Object View | Controls whether the Object View pane is visible or not. |
| Tag Editor | Controls whether the Tag Editor pane is visible or not. |
| Symbol Library | Controls whether the Symbol Library pane is visible or not. |
| Tag View | Controls whether the Tag View pane is visible or not. |
| Action View | Controls whether the Action View pane is visible or not. |
| Drawing Tools | Controls whether the Drawing Tools pane is visible or not. |
| Properties - Properties | Controls whether the Properties pane is visible or not. |
| Toolbars - Main Toolbar | Controls whether the Main Toolbar toolbar is visible or not. |
| Toolbars - Drawing Tools | Controls whether the Drawing Tools toolbar is visible or not. |
| Toolbars - Arrange Tools | Controls whether the Arrange Tools toolbar is visible or not. |
| Toolbars - Connection Tools | Controls whether the Connection Tools toolbar is visible or not. |
| Toolbars - Project Tools | Controls whether the Project Tools toolbar is visible or not. |
| Toolbars - Font Tools | Controls whether the Font Tools toolbar is visible or not. |
| Toolbars - State Selector Tools | Controls whether the State Selector Tools toolbar is visible or not. |
| Home Tab | Controls whether the Home Tab icon is visible or not. |
| Status Bar | Controls whether the Status Bar is visible or not. |
| Zoom | Opens a dropdown to select the magnification of the screen. The zoom percentages are 25%, 50%, 75%, 100%, 150%, 200%, and 400%. |
| Show Ruler | Controls whether the Ruler is visible or not. |
| Grid - 5 px | Sets the Snap to Grid size to be every 5 pixels. |
| Grid - 10 px | Sets the Snap to Grid size to be every 10 pixels. |
| Guides - Show Guides | Controls whether Guides are visible or not. Guides are vertical or horizontal lines that cross the entire page. |
| Guides - Add Vertical Guide | Creates a new vertical guide that can have its X position set. |
| Guides - Add Horizontal Guide | Creates a new horizontal guide that can have its Y position set. |
| Guides - Edit Guides | Opens the Edit Guides window where users can change the color and X or Y positions of guides. |
| Guides - Clear Guides | Deletes all guides. |
| Snap to - Grid | Controls whether objects will magnetize to each line in a grid between 5 or 10 pixels. |
| Snap to - Guide Lines | Controls whether objects will magnetize to created guide lines. |
| Snap to - Objects and Page | Controls whether objects will magnetize to other objects and the borders and midpoints. |
| Tag Overlay - None | Does not show any tag overlays on any objects. |
| Tag Overlay - All Objects | Shows all tag overlays on every object. |
| Tag Overlay - Selected Objects | Shows all tag overlays on selected objects. |
| Tag Overlay - Tag Path | The tag overlay information will show a tag icon and the tag’s path in the Tag Editor pane. |
| Tag Overlay - Tag Address | The tag overlay information will show a tag icon and the tag’s assigned I/O Address. |
Insert
Section titled “Insert”| Item | Description |
|---|---|
| Used to draw lines. | |
| Used to draw rectangles or squares. | |
| Used to draw circles or ellipses. | |
| Used to draw sectors of a circle. | |
| Used to draw arcs. | |
| Used to draw chords. | |
Used to draw polygons. Users can set how many sides, height, and width the polygon will be created with. ![]() | |
| Used to draw polylines. Drawing is started once the user clicks on the screen, and new vertices are added whenever the user left-clicks. To finish drawing, double-click or left-click the starting point. | |
| Used to display text. Double-click the text box to edit the initial value or go into binding properties and change the Initial Value of the text. The text can be changed during runtime by binding a tag to the label box. | |
| Used to display numbers. Double-click the numeric text box to edit the initial value or go into binding properties and change the Initial Value of the number. The number can be changed during runtime by binding a tag to the numeric text box. The formatting options of numbers are previewed and changed in the object's Properties pane. | |
| Used to import an image to the current page. Acceptable image formats are *.png, *.jpg, *.gif, *.jpeg, *.bmp, and *.svg. | |
| Used to input text during runtime. An action can be set to execute on enter. A tag may be bound to the text entry to store the entered value. Enabling autofocus will allow the field to be selected automatically on project startup. | |
| Used to input a number during runtime. An action can be set to execute on enter. A tag may be bound to the numeric entry to store the entered value. Enabling autofocus will allow the field to be selected automatically on project startup. | |
| Used to get the full file path of the selected file. A tag can be bound to the file path property. | |
| Used to create a switch/lamp object that displays a set image at each state. A tag may be bound to the switch/lamp object to change the state during runtime. Each state will display when the value of the bound tag matches the state number. Commands or scripts may be set to execute on press, on release, or on double-click. The most common use of a switch/lamp is to toggle a BOOL value on press to flip images off and on between states 0 and 1. | |
| Used to create a momentary button that displays a set image at three states: Inactive, Pressed, and Active. A tag must be bound to the momentary button before being able to save, and the tag is used to change the state during runtime. When pressed, the button will attempt to change the tag value to the On Press Value field and change it to the On Release Value field when released. The Inactive state will display when unpressed and the bound tag does not equal the On Press Value field. The Pressed state will display when pressed, and the bound tag does not equal the On Press Value field. The Active state will be shown when the bound tag is equal to the On Press Value field. Commands or scripts may be set to execute on press, on release, or on double-click. | |
| Used to create an action button that displays a set image at two states: Unpressed and Pressed. The Pressed state will display when the user is actively pressing the button, and the Unpressed state otherwise. Commands or scripts may be set to execute on press, on release, or on double-click. | |
| Used to create a toggle button that toggles a tag value. There are two states: inactive and active. Commands or scripts may be set to execute on press, on release, or on double-click. | |
| Used to create a combobox object that displays different choices, in menu format, to select from. The choice selection is controlled using an index which a tag can be bound to. | |
| Used to create a radio button group object that displays different choices, in list format, to select from. The choice selection is controlled using an index which a tag can be bound to. | |
| Used to create a checkbox to toggle between true or false. A tag can be bound to the value property. | |
| Used to draw a horizontal slider that represents a set Value field from Min Value and Max Value fields. All three fields may have a tag bound to them to change the values during runtime. The amount of steps and label/tick visibility can also be controlled. | |
| Used to draw a vertical slider that represents a set Value field from Min Value and Max Value fields. All three fields may have a tag bound to them to change the values during runtime. The amount of steps and label/tick visibility can also be controlled. | |
| Used to draw a round gauge that represents a set Value field from Min Value and Max Value fields. All three fields may have a tag bound to them to change the values during runtime. The amount of steps and label/tick visibility can also be controlled. | |
| Used to draw a horizontal gauge that represents a set Value field from Min Value and Max Value fields. All three fields may have a tag bound to them to change the values during runtime. The amount of steps and label/tick visibility can also be controlled. | |
| Used to draw a vertical gauge that represents a set Value field from Min Value and Max Value fields. All three fields may have a tag bound to them to change the values during runtime. The amount of steps and label/tick visibility can also be controlled. | |
| Used to display the system’s date and time with a set format. | |
| Used to draw a rectangle that fills based on a set Value field up to a set Max Value field. Both fields may have a tag bound to them to change the values during runtime. | |
| Used to create a trend graph to plot historical data. At least one tag must be bound to a pen of the trend before being able to save, and the bound tags are used to change the data points during runtime. | |
| Used to create a data log table that lists historical data in columns and rows. A data logger model with at least one tag must be bound to the data log table before being able to save, and the table will show the model's contents during runtime. | |
| Used to create an alarm summary that displays active, shelved, and historical alarm statuses. | |
| Used to create a trend line without the graphical interface from a Trend. A tag must be bound to the sparkline before being able to save, and the bound tag is used to change the data points during runtime. | |
| Used to create an audit log table that shows all of the actions users take in the form of a time, description, target, and value along with the user. The table can be filtered based on time interval and user and exported to a *.csv file format. | |
| Used to create an IP camera stream that displays a video feed from an IP camera in real time. | |
| Used to create a web browser that can access the internet with a stable connection. |
Arrange
Section titled “Arrange”| Item | Description |
|---|---|
| Order - | Selected objects are elevated to a 0 Z-index, commencing at zero and incrementing by one for each object on a page, placing them in front of all other objects. Groups are treated as one object with internal Z-indexing for only the group. ![]() |
| Order - | Decreases selected object’s Z-index by one, bringing it in front of objects with a higher Z-index. ![]() |
| Order - | Increases selected object’s Z-index by one, sending it behind objects with a lower Z-index. ![]() |
| Order - | Selected objects are lowered to the highest Z-index of a page, commencing at zero and incrementing by one for each object on a page, placing them behind all other objects. Groups are treated as one object with an internal Z-indexing for only the group. ![]() |
| Align - | Align all selected objects with the left edge of the leftmost selected object. Able to be used with two or more objects selected. ![]() |
| Align - | Align all selected objects to have the same x-value of the midpoint of all selected objects. Able to be used with two or more objects selected. ![]() |
| Align - | Align all selected objects with the right edge of the rightmost selected object. Able to be used with two or more objects selected. ![]() |
| Align - | Align all selected objects with the top edge of the topmost selected object. Able to be used with two or more objects selected. ![]() |
| Align - | Align all selected objects to have the same y-value of the midpoint of all selected objects. Able to be used with two or more objects selected. ![]() |
| Align - | Align all selected objects with the bottom edge of the bottommost selected object. Able to be used with two or more objects selected. ![]() |
| Distribute - | Align all selected objects evenly between the leftmost and rightmost selected objects. Able to be used with three or more objects selected. ![]() |
| Distribute - | Align all selected objects evenly between the topmost and bottommost selected objects. Able to be used with three or more objects selected. ![]() |
| Transform - | Rotates the selected objects using a customized rotation angle to its rotation center. |
| Transform - | Rotates the selected objects 90 degrees counterclockwise based on the rotation center. ![]() |
| Transform - | Rotates the selected objects 90 degrees clockwise based on the rotation center. ![]() |
| Transform - | Flips the selected objects horizontally based on the center point of the X-axis. ![]() |
| Transform - | Flips the selected objects horizontally based on the center point of the Y-axis. ![]() |
| Group | Combines all selected objects into one larger object. When clicking on any of the smaller objects, it will select all of them, allowing the user to move the objects simultaneously equally. Users can also add commands or scripts that will execute on press, release, or double-click for all objects in the group. |
| Ungroup | Uncombines all objects inside of a group. Any configuration or setting added to a group will be removed. |
| Show/Hide | Masks all selected objects that are not hidden or unmasks all selected objects that are hidden. Show/Hide prioritizes hiding objects, so all selected objects must be hidden to unmask. Hidden items can be selected by clicking their name in the object view pane. Objects can also be shown or hidden by clicking the Show/Hide eye icon next to their names in the object view pane. |
| Lock | Locks all selected objects, making them unchangeable or unselectable. Objects can also be locked or unlocked by clicking the lock icon next to their names in the object view pane. |
| Item | Description |
|---|---|
| Runs an instance of the project in the Canvas offline simulator. | |
| Runs an instance of the project in the Canvas online simulator that can connect to external devices. | |
| Opens the Connection Setup page, which allows users to connect to external devices via IP address for project transfer, VNC, and remote controls. | |
| Opens the I/O Device Editor window, which allows users to create devices that connect over Ethernet or serial over a common protocol. | |
| Opens the Data Server Editor window, which allows users to create a Modbus, MQTT, or OPC UA slave. | |
| Opens the Data Bridge Editor window, which allows users to bridge a connection between two devices that cannot communicate with each other. | |
| Opens the Tag Editor window, which allows users to create or edit tags. | |
| Opens the Script Editor window, which allows users to create or edit scripts. | |
| Opens the Recipe Editor window, which allows users to create, edit, or transfer recipes. | |
| Opens the Alarm Editor window, which allows users to create or edit alarms, alarm descriptions, and alarm summary labels. | |
| Opens the Data Log Editor window, which allows users to create or edit data log models that list historical data in columns and rows. | |
| Opens the Identity and Access Management window, which allows users to create or edit users, groups, and permissions. | |
| Opens the Schedule Editor, which allows users to set an action to execute at a specified time or time interval. | |
| Opens the String Table Editor, which allows users to add text as keys that can be easily changed to other languages. | |
| Opens the Cross Reference window, which allows users to search for all instances of a tag, script, page, or permission being used. |
| Item | Description |
|---|---|
| Help - Online | Opens the Canvas online help file. |
| Help - Offline | Opens the Canvas offline help file, a PDF of the online version. |
| About Canvas | Opens the About Canvas window that displays the currently installed Canvas version. |
Toolbar
Section titled “Toolbar”Main Tools
Section titled “Main Tools”| Item | Description |
|---|---|
| Creates a new graphic page for the project. | |
| Opens a file explorer window to select a “.cnvs” format project to launch its last-edited version. | |
| Saves the project’s current status. | |
| Copies the current project to a specified destination. | |
| Reverts the last non-undone action made. | |
| Reverts the last non-redone undo action made. | |
| Deletes the selected object’s content and saves it in the clipboard. | |
| Saves the selected object’s content in the clipboard. | |
| Pastes a cut or copied object from the clipboard. | |
| Resets the magnification of the workspace’s screen size to 100%. | |
| Increases the magnification of the workspace’s screen size over set intervals up to 400%. | |
| Decreases the magnification of the workspace’s screen size over set intervals down to 25%. |
Drawing Tools
Section titled “Drawing Tools”| Item | Description |
|---|---|
| Used to stop drawing. | |
| Used to draw lines. | |
| Used to draw rectangles or squares. | |
| Used to draw circles or ellipses. | |
| Used to draw sectors of a circle. | |
| Used to draw arcs. | |
| Used to draw chords. | |
Used to draw polygons. Users can set how many sides, height, and width the polygon will be created with. ![]() | |
| Used to draw polylines. Drawing is started once the user clicks on the screen, and new vertices are added whenever the user left-clicks. To finish drawing, double-click or left-click the starting point. | |
| Used to display text. Double-click the text box to edit the initial value or go into binding properties and change the Initial Value of the text. The text can be changed during runtime by binding a tag to the label box. | |
| Used to display numbers. Double-click the numeric text box to edit the initial value or go into binding properties and change the Initial Value of the number. The number can be changed during runtime by binding a tag to the numeric text box. The formatting options of numbers are previewed and changed in the object's Properties pane. | |
| Used to import an image to the current page. Acceptable image formats are *.png, *.jpg, *.gif, *.jpeg, *.bmp, and *.svg. | |
| Used to input text during runtime. An action can be set to execute on enter. A tag may be bound to the text entry to store the entered value. Enabling autofocus will allow the field to be selected automatically on project startup. | |
| Used to input a number during runtime. An action can be set to execute on enter. A tag may be bound to the numeric entry to store the entered value. Enabling autofocus will allow the field to be selected automatically on project startup. | |
| Used to get the full file path of the selected file. A tag can be bound to the file path property. | |
| Used to create a switch/lamp object that displays a set image at each state. A tag may be bound to the switch/lamp object to change the state during runtime. Each state will display when the value of the bound tag matches the state number. Commands or scripts may be set to execute on press, on release, or on double-click. The most common use of a switch/lamp is to toggle a BOOL value on press to flip images off and on between states 0 and 1. | |
| Used to create a momentary button that displays a set image at three states: Inactive, Pressed, and Active. A tag must be bound to the momentary button before being able to save, and the tag is used to change the state during runtime. When pressed, the button will attempt to change the tag value to the On Press Value field and change it to the On Release Value field when released. The Inactive state will display when unpressed and the bound tag does not equal the On Press Value field. The Pressed state will display when pressed, and the bound tag does not equal the On Press Value field. The Active state will be shown when the bound tag is equal to the On Press Value field. Commands or scripts may be set to execute on press, on release, or on double-click. | |
| Used to create an action button that displays a set image at two states: Unpressed and Pressed. The Pressed state will display when the user is actively pressing the button, and the Unpressed state otherwise. Commands or scripts may be set to execute on press, on release, or on double-click. | |
| Used to create a toggle button that toggles a tag value. There are two states: inactive and active. Commands or scripts may be set to execute on press, on release, or on double-click. | |
| Used to create a combobox object that displays different choices, in menu format, to select from. The choice selection is controlled using an index which a tag can be bound to. | |
| Used to create a radio button group object that displays different choices, in list format, to select from. The choice selection is controlled using an index which a tag can be bound to. | |
| Used to create a checkbox to toggle between true or false. A tag can be bound to the value property. | |
| Used to draw a horizontal slider that represents a set Value field from Min Value and Max Value fields. All three fields may have a tag bound to them to change the values during runtime. The amount of steps and label/tick visibility can also be controlled. | |
| Used to draw a vertical slider that represents a set Value field from Min Value and Max Value fields. All three fields may have a tag bound to them to change the values during runtime. The amount of steps and label/tick visibility can also be controlled. | |
| Used to draw a round gauge that represents a set Value field from Min Value and Max Value fields. All three fields may have a tag bound to them to change the values during runtime. The amount of steps and label/tick visibility can also be controlled. | |
| Used to draw a horizontal gauge that represents a set Value field from Min Value and Max Value fields. All three fields may have a tag bound to them to change the values during runtime. The amount of steps and label/tick visibility can also be controlled. | |
| Used to draw a vertical gauge that represents a set Value field from Min Value and Max Value fields. All three fields may have a tag bound to them to change the values during runtime. The amount of steps and label/tick visibility can also be controlled. | |
| Used to display the system’s date and time with a set format. | |
| Used to draw a rectangle that fills based on a set Value field up to a set Max Value field. Both fields may have a tag bound to them to change the values during runtime. | |
| Used to create a trend graph to plot historical data. At least one tag must be bound to a pen of the trend before being able to save, and the bound tags are used to change the data points during runtime. | |
| Used to create a data log table that lists historical data in columns and rows. A data logger model with at least one tag must be bound to the data log table before being able to save, and the table will show the model's contents during runtime. | |
| Used to create an alarm summary that displays active, shelved, and historical alarm statuses. | |
| Used to create a trend line without the graphical interface from a Trend. A tag must be bound to the sparkline before being able to save, and the bound tag is used to change the data points during runtime. | |
| Used to create an audit log table that shows all of the actions users take in the form of a time, description, target, and value along with the user. The table can be filtered based on time interval and user and exported to a *.csv file format. | |
| Used to create an IP camera stream that displays a video feed from an IP camera in real time. | |
| Used to create a web browser that can access the internet with a stable connection. |
Arrange Tools
Section titled “Arrange Tools”| Item | Description |
|---|---|
Selected objects are elevated to a 0 Z-index, commencing at zero and incrementing by one for each object on a page, placing them in front of all other objects. Groups are treated as one object with internal Z-indexing for only the group. ![]() | |
Decreases selected object’s Z-index by one, bringing it in front of objects with a higher Z-index. ![]() | |
Increases selected object’s Z-index by one, sending it behind objects with a lower Z-index. ![]() | |
Selected objects are lowered to the highest Z-index of a page, commencing at zero and incrementing by one for each object on a page, placing them behind all other objects. Groups are treated as one object with an internal Z-indexing for only the group. ![]() | |
Align all selected objects with the left edge of the leftmost selected object. Able to be used with two or more objects selected. ![]() | |
Align all selected objects to have the same x-value of the midpoint of all selected objects. Able to be used with two or more objects selected. ![]() | |
Align all selected objects with the right edge of the rightmost selected object. Able to be used with two or more objects selected. ![]() | |
Align all selected objects with the top edge of the topmost selected object. Able to be used with two or more objects selected. ![]() | |
Align all selected objects to have the same y-value of the midpoint of all selected objects. Able to be used with two or more objects selected. ![]() | |
Align all selected objects with the bottom edge of the bottommost selected object. Able to be used with two or more objects selected. ![]() | |
Align all selected objects evenly between the leftmost and rightmost selected objects. Able to be used with three or more objects selected. ![]() | |
Align all selected objects evenly between the topmost and bottommost selected objects. Able to be used with three or more objects selected. ![]() | |
| Rotates the selected objects using a customized rotation angle to its rotation center. | |
Rotates the selected objects 90 degrees clockwise based on the rotation center. ![]() | |
Rotates the selected objects 90 degrees counterclockwise based on the rotation center. ![]() | |
Flips the selected objects horizontally based on the center point of the X-axis. ![]() | |
Flips the selected objects horizontally based on the center point of the Y-axis. ![]() |
Connections Tools
Section titled “Connections Tools”| Item | Description |
|---|---|
| Opens the Connection Setup page, which allows users to connect to external devices via IP address for project transfer, VNC, and remote controls. | |
| Downloads the project from the host to the selected device. | |
| Uploads the project from the selected device to the host. | |
| Runs an instance of the project in the Canvas offline simulator. | |
| Runs an instance of the project in the Canvas online simulator that can connect to external devices. |
Project Tools
Section titled “Project Tools”| Item | Description |
|---|---|
| Opens the I/O Device Editor window, which allows users to create devices that connect over Ethernet or serial over a common protocol. | |
| Opens the Data Server Editor window, which allows users to create a Modbus, MQTT, or OPC UA slave. | |
| Opens the Data Bridge Editor window, which allows users to bridge a connection between two devices that cannot communicate with each other. | |
| Opens the Tag Editor window, which allows users to create or edit tags. | |
| Opens the Script Editor window, which allows users to create or edit scripts. | |
| Opens the Recipe Editor window, which allows users to create, edit, or transfer recipes. | |
| Opens the Alarm Editor window, which allows users to create or edit alarms, alarm descriptions, and alarm summary labels. | |
| Opens the Data Log Editor window, which allows users to create or edit data log models that list historical data in columns and rows. | |
| Opens the Identity and Access Management window, which allows users to create or edit users, groups, and permissions. | |
| Opens the Schedule Editor, which allows users to set an action to execute at a specified time or time interval. | |
| Opens the String Table Editor, which allows users to add text as keys that can be easily changed to other languages. | |
| Opens the Cross Reference window, which allows users to search for all instances of a tag, script, page, or permission being used. |
Font Tools
Section titled “Font Tools”| Item | Description |
|---|---|
| Font | Changes the style of text. |
| Allows the user to install custom fonts not available by default. | |
| Size | Changes the size of the text. |
| Color | Changes the color of the text. |
| Bold the selected text. | |
| Italicize the selected text. | |
| Underline the selected text. | |
| Align the text to the left of the text box. | |
| Align the text to the center of the text box. | |
| Align the text to the right of the text box. | |
| Align the text to the top of the text box. | |
| Align the text to the center of the text box. | |
| Align the text to the bottom of the text box. |
State Selector Tools
Section titled “State Selector Tools”| Item | Description |
|---|---|
| Displays the current state of the Switch/Lamp object. | |
| Decreases the Switch/Lamp state view. | |
| Increases the Switch/Lamp state view. |